AIP Supplement – ÍSLAND / ICELAND
|
Isavia ANS ehf., Reykjavíkurflugvelli, 102 Reykjavík /
Isavia ANS, Reykjavik Airport, IS-102 Reykjavik, Iceland
Sími / Telephone: + 354 424 4000
ais@isavia.is
http://www.isavia.is/
|
|
|
|
Effective from 17 MAY 2024
Published on 17 MAY 2024
|
|
|
|
KEFLAVÍK - Framkvæmdir við Austurvæng og flughlaðið (SLN18 & NTA22) /
KEFLAVIK - Construction work at East wing and apron (SLN18 & NTA22)
|
|
Content Responsibility: Isavia, Keflavik Airport
|
|
|
Work related to the new construction of East Wing building, along with the reconstruction of the apron south of the new East Wing.
|
|
It is estimated that the construction work will continue at the apron until the end of 2024.
|
It is estimated that four new code C stands will be operational in September 2024.
|
The impact of the construction will be communicated via NOTAM if necessary.
|
|
The new construction will expand the north building towards the east and increase the size of the commercial, catering, and service areas of the airport.
|
Four new stands will be built in connection with the new construction, and the execution will be carried out in phases.
|
1.3 Impact from construction site on flight safety
|
Stand 2 will be permanently closed.
|
Stand 4 will be closed for an indefinite period.
|
Stands 78, 76, and 74 have been permanently downgraded to code C stands.
|
A fence will be erected around the construction area, which will narrow the taxiway clearances on the apron during the construction period.
|
|
|
1.4 Current construction zone
|
|
|
1.5 Opening layout of new stands
|
|
|
|
The following may be contacted for information or to provide feedback:
|
|
|
AIP Supplement cancelled:
|
|
|
NOTAM incorporated in this Supplement:
|
|
|
|