AIP Supplement – ÍSLAND / ICELAND
Isavia ANS ehf., Reykjavíkurflugvelli, 102 Reykjavík /
Isavia ANS, Reykjavik Airport, IS-102 Reykjavik, Iceland
Sími / Telephone: + 354 424 4000
ais@isavia.is
http://www.isavia.is/

 
AIP SUP nr 07/2024
Effective from  17 MAY 2024
Published on 17 MAY 2024
 

 
KEFLAVÍK - Framkvæmdir við Austurvæng og flughlaðið (SLN18 & NTA22) /
KEFLAVIK - Construction work at East wing and apron (SLN18 & NTA22)

Content Responsibility: Isavia, Keflavik Airport

1 Introduction

Work related to the new construction of East Wing building, along with the reconstruction of the apron south of the new East Wing.

1.1 Estimated validity

It is estimated that the construction work will continue at the apron until the end of 2024. 
It is estimated that four new code C stands will be operational in September 2024.
The impact of the construction will be communicated via NOTAM if necessary.

1.2 Project

The new construction will expand the north building towards the east and increase the size of the commercial, catering, and service areas of the airport.
Four new stands will be built in connection with the new construction, and the execution will be carried out in phases.

1.3 Impact from construction site on flight safety

Stand 2 will be permanently closed.
 
Stand 4 will be closed for an indefinite period.
Stands 78, 76, and 74 have been permanently downgraded to code C stands.
A fence will be erected around the construction area, which will narrow the taxiway clearances on the apron during the construction period.

 


 

 
 

1.4 Current construction zone

 
 

1.5 Opening layout of new stands

 
 

2 Contacts

The following may be contacted for information or to provide feedback:
 

 
 AIP Supplement cancelled:
SUP 14/2023
 

 

 
NOTAM incorporated in this Supplement:
NIL
 
END